Stem, North Carolina (27581) · Butner, North Carolina (27509) · Creedmoor, North Carolina (27522) · Oxford, North Carolina (27565) · Franklinton, North Carolina (27525) · Youngsville, North Carolina (27596) · Durham, North Carolina (27701) · Wake Forest, North Carolina (27587) · Hillsborough, North Carolina (27278) · Henderson, North Carolina (27536) · North Raleigh, North Carolina (27614, 27615).
Use a single item register
For each item, record the agreed scope, assigned trade, date worked, before and after evidence, test or inspection needed, reviewer and status: open, ready for review, accepted or disputed. Note any access delay or missing material without marking the item complete.
For doors and hardware, verify operation; for finishes, compare the agreed repair area and appearance; for equipment or systems, use the qualified trade's commissioning or test record where the contract requires it. Do not substitute a photograph for a required inspection.
Separate milestones
AIA's substantial-completion documents treat remaining items and closeout obligations as distinct matters. The date a space is usable, the date a punch item is corrected, final acceptance, final payment and warranty start can differ under the actual contract. Ask the project team to record each milestone instead of treating a single 'done' checkbox as all of them.
Keep the signed change record, inspection results, manuals or warranties owed, final list of exceptions and responsible contacts together. If an item is disputed, state what evidence or decision is needed to resolve it.
Plan callbacks and payment records
Agree who reports a recurring defect, the response process, exclusions and any return-visit charges. Reconcile accepted items and approved changes to invoices, credits and payments once; a deposit and later balance are parts of one job, not two jobs.
Common questions
Does substantial completion mean every punch item is finished?
No. AIA forms contemplate a list of remaining work; the actual contract and project team determine the milestones and obligations.
Can I close an item from a photo?
A photo may help, but operation, finish, inspection or other acceptance criteria may require an on-site check.
What if a new problem appears during closeout?
Record it separately, determine whether it is agreed corrective work or an added scope, and obtain the required approval before work.